Installations

GE Installation

Project: Clear Lake/Clearwater Sanitary Dictrict – 1st Municipal MBR in the State of MN
Engineer: Bonestroo

Contractor:
Phase I – City Staff
Phase II – Gridor


Design:               
Phase I  - 120,000  GPD ADF
Phase II – 360,000 GPD ADF


Equipment:       
Phase I – GE/Zenon ZMOD; two (2) Membrane Tanks, permeate skid, controls, chemical feed, membrane air scour blower, recirculation pumps
Phase II – Duplicate of Phase I

Notes:
1. CLCW have received a waiver so that they do not need to disinfect
 

CLCW 12-20-07
CLCW 12-20-07