GE Installation
Project: Clear Lake/Clearwater Sanitary Dictrict – 1st Municipal MBR in the State of MN
Engineer: Bonestroo
Contractor:
Phase I – City Staff
Phase II – Gridor
Design:
Phase I - 120,000 GPD ADF
Phase II – 360,000 GPD ADF
Equipment:
Phase I – GE/Zenon ZMOD; two (2) Membrane Tanks, permeate skid, controls, chemical feed, membrane air scour blower, recirculation pumps
Phase II – Duplicate of Phase I
Notes:
1. CLCW have received a waiver so that they do not need to disinfect