GE Installation - Cold Spring, MN
Project: Goldn Plump; Cold Spring, MN
Engineers: MFRA – Tom Barron; Bob Peplin
Installation Contractor: Rice Lake
Design: Modified Bardenpho, Enhanced Biological Nitrate and Phosphorus (EBPR).
Flow: up to 2.1 MGD, COD – 1300, BOD – 650, TSS – 190, TKN – 100, Alk – 560, Nitrate – 2, NH3-N – 27, TP-14.
Guaranty: BOD - <5, TSS - <5, NH3 - <1, TN - <10, TP-<4
Equipment: Four (4) Trains of GE/Zenon ZW500
Tanks: Anaerobic, Anoxic, Aeration, Membrane, Post Anoxic
Notes: a. The plant is slated for startup in the 3rd Q, 2010.
b. The pictures show the air and permeate piping in a room above the Membrane Tanks.
Also the Permeate and Backpulse pumps in a room adjacent to the Membrane Tanks.