GE Installation - Valley City, ND
Project: Valley City, ND – WTP Retrofit – Integrated UF/RO
Engineer: AE2S - Grand Forks
Contractor: Swanberg Construction, Valley City
Source water: Sheyenne River and GW wells
The Picture: Taken in Febr., 2011. The view is into the old clarifier basin that is being retrofitted to house the new ZW1000 membranes. Start up is scheduled for late 2011/early 2012
Equipment:
3 - GE Muni 1.0MGD RO Skids – total permeate flow = 3.0 MGD
Membrane: GE-RO-400-LE-HR-WT
2 - DeLoach Degasifiers
1400 GPM each @ 5000 CFM/each
4 - GE W&PT ZW1000 UF Trains, three (3) cassettes/train
5 MGD Design Flow @ 1C